Question: The activity table is given below Activity Predecessor 0-1 Clear site 1-2 Survey and layout 2 5 Rough grade 2 7 3-4 Drill wel 15

The activity table is given below Activity
The activity table is given below Activity Predecessor 0-1 Clear site 1-2 Survey and layout 2 5 Rough grade 2 7 3-4 Drill wel 15 22 3-6 Water tank foundations 4 12 3-9 Excavate sewer 10 21 3-10 Excavate electrical manholes 1 21 3-12 Pole line 6 7 29 4-5 Well pump 2 22 24 a Draw the CPM network with path duration and determine the critical path b. Draw the CPM path with ES, EFLS.LF and determine the critical path 2-3 (10) Duration 3 ES 0 3 5 7 7 7 7 LF 3