Question: The activity table is given below Activity Predecessor Duration ES LE 0-1 Clear site 3 1-2 Survey and layout 2 2-3 Rough grade 2 7
The activity table is given below
Activity
Predecessor
Duration
ES
LE
0-1
Clear site
3
1-2
Survey and layout
2
2-3
Rough grade
2
7
3-4
Drill wel
15
22
3-6
Water tank foundations
4
12
3-9
Excavate sewer
10
21
3-10
Excavate electrical manholes
1
21
3-12
Pole line
6
29
4-5
2
22
Well pump.
24
a) Draw the CPM network with path duration and determine the critical path
b) Draw the CPM path with ES, EF,LS,LF and determine the critical path