Question: The activity table is given below Activity Predecessor Duration ES LE 0-1 Clear site 3 1-2 Survey and layout 2 2-3 Rough grade 2 7

The activity table is given below
Activity
Predecessor
Duration
ES
LE
0-1
Clear site
3
1-2
Survey and layout
2
2-3
Rough grade
2
7
3-4
Drill wel
15
22
3-6
Water tank foundations
4
12
3-9
Excavate sewer
10
21
3-10
Excavate electrical manholes
1
21
3-12
Pole line
6
29
4-5
2
22
Well pump.
24
a) Draw the CPM network with path duration and determine the critical path
b) Draw the CPM path with ES, EF,LS,LF and determine the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!