Question: The activity table is given below 22/051 given Activity Predecessor ES LF 0-1 Clear site 0 3 1-2 Survey and layout 3 5 2-3 Rough

The activity table is given below 22/051 given

The activity table is given below 22/051 given Activity Predecessor ES LF 0-1 Clear site 0 3 1-2 Survey and layout 3 5 2-3 Rough grade 5 7 3-4 Drill wel 7 22 3-6 Water tank foundations 7 12 3-9 Excavate sewer 7 21 3-10 Excavate electrical manholes 7 21 3-12 Pole line 7 29 4-5 Well pump 22 24 a. Draw the CPM network with path duration and determine the critical path b. Draw the CPM path with ES, EF,LS,LF and determine the critical path (10) Duration 3 2 2 15 4 10 1 62