Question: on a CPM network has predecessors N and R, and has successor S. M has duration 5. N has a late finish 18, while R

on a CPM network has predecessors N and R, and has successor S. M has duration 5. N has a late finish 18, while R has late finish of 20. Which of the following is true?

A.

N is a critical activity.

B.

The late start time of S is 23.

C.

The late start time of S is 25.

D.

M is critical and has zero slack.

E.

M has no slack but is not critical.