Question: on a CPM network has predecessors N and R, and has successor S. M has duration 5. N has a late finish 18, while R
on a CPM network has predecessors N and R, and has successor S. M has duration 5. N has a late finish 18, while R has late finish of 20. Which of the following is true?
| A. | N is a critical activity. | |
| B. | The late start time of S is 23. | |
| C. | The late start time of S is 25. | |
| D. | M is critical and has zero slack. | |
| E. | M has no slack but is not critical. |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
