Question: QUESTION 1 3 Consider the following work breakdown structure: table [ [ Duration Estimates ( Days ) ] , [ Activity , Precedes,Optimistic,Most Likely,Pessimistio

QUESTION 13
Consider the following work breakdown structure:
\table[[Duration Estimates (Days)],[Activity,Precedes,Optimistic,Most Likely,Pessimistio],[Start,?bar(U,V),-,-,-],[U,W,35,50,65],[V,W,x,28,40,52],[W,Z,26,35,44],[x,?bar(Y),28,40,52],[Y,Z,26,29,38],[Z,End,36,60,84],[{
\table[[What is the estimated standard deviation in the time for activity Z?],[3 days]]}],[],[8 days],[5 days],[4 days],[2 days,,,,]]
 QUESTION 13 Consider the following work breakdown structure: \table[[Duration Estimates (Days)],[Activity,Precedes,Optimistic,Most