Question: QUESTION 1 3 Consider the following work breakdown structure: table [ [ Duration Estimates ( Days ) ] , [ Activity , Precedes,Optimistic,Most Likely,Pessimistio
QUESTION
Consider the following work breakdown structure:
tableDuration Estimates DaysActivityPrecedes,Optimistic,Most Likely,PessimistioStartWVWZYZZEnd,
tableWhat is the estimated standard deviation in the time for activity Z days days days days days,,,,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
