Question: QUESTION FOUR [ 2 0 ] Using the information from the table below, answer the questions that follows table [ [ Activity , Predecessor,Optimistic

QUESTION FOUR
[20]
Using the information from the table below, answer the questions that follows
\table[[Activity,Predecessor,Optimistic Time,Most Likely Time,Pessimistic time],[A,-,1,4,7],[B,-,2,6,10],[C,B,3,3,9],[D,A,6,13,14],[E,A,C,4,6,14],[F,B,6,8,16],[G,D,E,F,2,5,8]]
4.1. Calculate each activity expected time (in days)
(7)
4.2. Complete the table below and calculate the critical path using the slack values. You are not required to show the network diagram
(13)QUESTION FOUR
[20]
Using the information from the table below, answer the questions that follows
\table[[Activity,Predecessor,Optimistic Time,Most Likely Time,Pessimistic time],[A,-,1,4,7],[B,-,2,6,10],[C,B,3,3,9],[D,A,6,13,14],[E,A,C,4,6,14],[F,B,6,8,16],[G,D,E,F,2,5,8]]
4.1. Calculate each activity expected time (in days)
(7)
4.2. Complete the table below and calculate the critical path using the slack values. You are not required to show the network diagram
(13)QUESTION FOUR
[20]
Using the information from the table below, answer the questions that follows
\table[[Activity,Predecessor,Optimistic Time,Most Likely Time,Pessimistic time],[A,-,1,4,7],[B,-,2,6,10],[C,B,3,3,9],[D,A,6,13,14],[E,A,C,4,6,14],[F,B,6,8,16],[G,D,E,F,2,5,8]]
4.1. Calculate each activity expected time (in days)
(7)
4.2. Complete the table below and calculate the critical path using the slack values. You are not required to show the network diagram
(13)
 QUESTION FOUR [20] Using the information from the table below, answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!