Question: Seven jobs are to be processed through a single machine. The processing times and due dates are given below. Job Processing Time Due Date
Seven jobs are to be processed through a single machine. The processing times and due dates are given below. Job Processing Time Due Date 1 3 4 2 6 8 3 8 16 4 4 10 Determine the sequence of the jobs in order to minimize (a) mean flow time (hint: SPT) 5 2 11 6 1 23 7 7 21 (b) number of tardy jobs (hint: Moore's algorithm) (c) maximum lateness (hint: EDD or Lawler's algorithm without precedence constraints).
Step by Step Solution
3.52 Rating (159 Votes )
There are 3 Steps involved in it
a Most limited Processing Time SPT rule assists with limiting the mean stream season of a task Subse... View full answer