Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 -- B 2 A C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 4 | -- |
| B | 2 | A |
| C | 9 | -- |
| D | 4 | A |
| E | 5 | B,C,D |
| a | A-D-E; 15 | |
| b | A-B-C-D-E; 22 | |
| c | C-E; 14 | |
| d | A-B-E; 11 | |
| e | A-B-D; 10 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
