Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 -- B 2 A C

The critical path for the network activities shown below is ________ with duration ________.

Activity

Duration

Immediate

Predecessors

A 4 --
B 2 A
C 9 --
D 4 A
E 5 B,C,D
a A-D-E; 15
b A-B-C-D-E; 22
c C-E; 14
d A-B-E; 11
e A-B-D; 10