Question: The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate A 4 --- B 2 A C 7
The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate A 4 --- B 2 A C 7 -- D 4 A E 5 B,C,D
a.
A-B-C-D-E; 22
b.
A-D-E; 13
c.
A-D-E; 11
d.
A-B-E; 11
e.
A-B-D; 10