Question: The critical path for the network activities shown below is _____ with duration ______.Activity Duration Immediate A 4 ---B 2 AC 7 --D 4 AE
The critical path for the network activities shown below is _____ with duration ______.Activity Duration Immediate A 4 ---B 2 AC 7 --D 4 AE 5 B,C,D
a. A-D-E; 13
b. A-B-D; 10
c. A-B-E; 11
d. A-D-E; 11
e. A-B-C-D-E; 22