Question: The critical path for the project activities shown below is ________ with duration ________. Activity Activity Time (in weeks ) Immediate Predecessor(s) A 10 ---
The critical path for the project activities shown below is ________ with duration ________.
| Activity | Activity Time (in weeks) | Immediate Predecessor(s) |
| A | 10 | --- |
| B | 8 | A |
| C | 2 | A |
| D | 4 | C |
| E | 5 | B, C |
Group of answer choices
A-B-E; 23 weeks
A-B-C-E; 25 weeks
A-C-E; 17 weeks
B-C-E; 15 weeks
A-C-D; 16 weeks