Question: The critical path for the project activities shown below is ________ with duration ________. Activity Activity Time (in weeks ) Immediate Predecessor(s) A 8 ---
The critical path for the project activities shown below is ________ with duration ________.
| Activity | Activity Time (in weeks) | Immediate Predecessor(s) |
| A | 8 | --- |
| B | 5 | --- |
| C | 3 | --- |
| D | 6 | A, C |
| E | 2 | B |
| F | 4 | D, E |
Group of answer choices
A-C-D-F; 21 weeks
B-E-F; 11 weeks
A-B-E-F; 19 weeks
C-D-F; 13 weeks
A-B-D; 19 weeks
A-D-F; 18 weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
