Question: The critical path for the project activities shown below is ________ with duration ________. Activity Activity Time (in weeks ) Immediate Predecessor(s) A 8 ---

The critical path for the project activities shown below is ________ with duration ________.

Activity Activity Time (in weeks) Immediate Predecessor(s)
A 8 ---
B 5 ---
C 3 ---
D 6 A, C
E 2 B
F 4 D, E

Group of answer choices

A-C-D-F; 21 weeks

B-E-F; 11 weeks

A-B-E-F; 19 weeks

C-D-F; 13 weeks

A-B-D; 19 weeks

A-D-F; 18 weeks