Question: The critical path for the project activities shown below is ________ with duration ________. Activity Activity Time (in weeks) Immediate Predecessor(s) A 10 --- B
The critical path for the project activities shown below is ________ with duration ________. Activity Activity Time (in weeks) Immediate Predecessor(s) A 10 --- B 8 A C 2 B D 4 B E 5 C, D