Question: The expected activity time in PERT analysis is calculated as: the sum of the optimistic, persimistic, and most lakly times, divided by six. the sum

The expected activity time in PERT analysis is calculated as:
the sum of the optimistic, persimistic, and most lakly times, divided by six.
the sum of the activity variances, divided by six.
the simple average of the optimistic, pessimistic, and most likeiy times. The form of the optimister pecimaistic, and mast likely times. The weighted aytrage of a m, and b wich wn weighed 4 times as heavily as a and b.
 The expected activity time in PERT analysis is calculated as: the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!