Question: The expected activity time in PERT analysis is calculated as: the sum of the optimistic, persimistic, and most lakly times, divided by six. the sum
The expected activity time in PERT analysis is calculated as:
the sum of the optimistic, persimistic, and most lakly times, divided by six.
the sum of the activity variances, divided by six.
the simple average of the optimistic, pessimistic, and most likeiy times. The form of the optimister pecimaistic, and mast likely times. The weighted aytrage of a m and b wich wn weighed times as heavily as a and b
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
