Question: There are five activities on a projects critical path and they have standard deviations of 3, 4, 4, 6, 6 days. The standard deviation (in

There are five activities on a projects critical path and they have standard deviations of 3, 4, 4, 6, 6 days. The standard deviation (in days) of the critical path is:

A.

10.2

B.

8.8

C.

7.8

D.

4.6

E.

9.8

F.

10.6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!