Question: There are five activities on a projects critical path and they have standard deviations of 3, 4, 4, 6, 6 days. The standard deviation (in

There are five activities on a projects critical path and they have standard deviations of 3, 4, 4, 6, 6 days. The standard deviation (in days) of the critical path is:

A.

7.8

B.

9.8

C.

10.6

D.

4.6

E.

10.2

F.

8.8