Question: There are five activities on a projects critical path and they have standard deviations of 2, 2, 5, 6, 6 days. The standard deviation (in
There are five activities on a projects critical path and they have standard deviations of 2, 2, 5, 6, 6 days. The standard deviation (in days) of the critical path is: A. 8.8 B. 10.6 C. 9.8 D. 7.8