Question: There are five activities on a projects critical path and they have standard deviations of 2, 2, 4, 6, 6 days. The standard deviation (in
There are five activities on a projects critical path and they have standard deviations of 2, 2, 4, 6, 6 days. The standard deviation (in days) of the critical path is:
| A. | 10.6 | |
| B. | 9.8 | |
| C. | 10.2 | |
| D. | 8.8 | |
| E. | 7.8 | |
| F. | 4.6 |