Question: use CCPM for the 2 projects bellow: Project Design Production Training Deadline Penalty A 4 weeks 8 weeks 4 weeks Week 20 $50K/week B 8
use CCPM for the 2 projects bellow:
| Project | Design | Production | Training | Deadline | Penalty |
| A | 4 weeks | 8 weeks | 4 weeks | Week 20 | $50K/week |
| B | 8 weeks | 12 weeks | 4 week | Week 25 | $30K/week |
| Given the due dates and penalties, schedule A activities before B, using one design crew, one production crew, and one training crew. Show each step of the critical chain analysis. |
How many buffers and what type of buffers?