Question: use CCPM for the 2 projects bellow: Project Design Production Training Deadline Penalty A 4 weeks 8 weeks 4 weeks Week 20 $50K/week B 8

use CCPM for the 2 projects bellow:

Project Design Production Training Deadline Penalty
A 4 weeks 8 weeks 4 weeks Week 20 $50K/week
B 8 weeks 12 weeks 4 week Week 25 $30K/week
Given the due dates and penalties, schedule A activities before B, using one design crew, one production crew, and one training crew. Show each step of the critical chain analysis.

How many buffers and what type of buffers?