Question: You have been asked to evaluate a project performance using earned value management techniques. It is currently day 52.60 of a project. BCWS, BCWP, and
You have been asked to evaluate a project performance using earned value management techniques. It is currently day 52.60 of a project. BCWS, BCWP, and AC to dateare 20.49m, 25.60m, and 24.54m respectively. Then what isthe CV of the project to date?
(Please keep two decimal points if applicable. Do not include unit "m"-million in your answers. For example, if your answer is 10 m, just write 10, not 10m or 10,000,000.)