Question: Using the information given, calculate the variance for each of the projectactivities. Most Optimistic Likely Pessimistic Time Time Time Estimate Estimates Estimates Immediate Activity (weeks
.png)
Most Optimistic Likely Pessimistic Time Time Time Estimate Estimates Estimates Immediate Activity (weeks (weeks) (eks) Predecessor(s one 12 16 10 4 D, E D, E 10 H, I
Step by Step Solution
3.39 Rating (165 Votes )
There are 3 Steps involved in it
Activity A B C ... View full answer