Question: Using the information given, calculate the variance for each of the projectactivities. Most Optimistic Likely Pessimistic Time Time Time Estimate Estimates Estimates Immediate Activity (weeks

Using the information given, calculate the variance for each of the projectactivities.
Using the information given, calculate the variance for each of

Most Optimistic Likely Pessimistic Time Time Time Estimate Estimates Estimates Immediate Activity (weeks (weeks) (eks) Predecessor(s one 12 16 10 4 D, E D, E 10 H, I