Question: 3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Predecessors Activity Time (in hours) A

3.7 Task time estimates for a production line

3.7 Task time estimates for a production line setup project at Robert Klassen's Ontario factory are as follows: Immediate Predecessors Activity Time (in hours) A 6.0 A B D E F B, C 7.2 5.0 6.0 4.5 7.7 4.0 B,C D E, F a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length? d) Draw a Gantt chart for the project