Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Immediate Predecessor(s) Activity Time (weeks) 2 . B 8

A project for improving a billing process has the following precedence relationships and activity times:

A project for improving a billing process has the

A project for improving a billing process has the

Activity Immediate Predecessor(s) Activity Time (weeks) 2 . B 8 5 D 12 A B, C B E 10 4 D LUI 8 E 7 F, G Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) A 2 B 8 C 5 D 12 E 10 F 4 8 U I 7 V