Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Immediate Predecessor(s) Activity Time (weeks) 2 A B 8

A project for improving a billing process has the

A project for improving a billing process has the

A project for improving a billing process has the following precedence relationships and activity times: Activity Immediate Predecessor(s) Activity Time (weeks) 2 A B 8 C 7 A D 11 B, C B E 9 4 D LUI 4 E 9 F, G a. Choose the correct network diagram below. O A. OB. A A 11 2 7 D F H 4 S 11 4 9 B B E G - 8 9 4 O c. D. F A 2 7 4 2 F. H S S F 9 9 11 4 9 B D B E G 8 11 4. 8 9 4