Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Processors A 2 -- B
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Processors |
| A | 2 | -- |
| B | 10 | -- |
| C | 8 | A |
| D | 12 | B,C |
| E | 11 | B |
| F | 4 | D |
| G | 7 | E |
| H | 6 | F,G |
-Calculate the slack for each activity. Which activities are on the critical path? Solve for "?".
| Activity | Activity Time (weeks) | On Critical Path? (Answer yes or no) | Slack (Weeks) |
| A | 2 | ? | ? |
| B | 10 | ? | ? |
| C | 8 | ? | ? |
| D | 12 | ? | ? |
| E | 11 | ? | ? |
| F | 4 | ? | ? |
| G | 7 | ? | ? |
| H | 6 | ? | ? |