Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Processors A 2 -- B

A project for improving a billing process has the following precedence relationships and activity times:

Activity

Activity Time (weeks)

Immediate Processors

A

2

--

B

10

--

C

8

A

D

12

B,C

E

11

B

F

4

D

G

7

E

H

6

F,G

-Calculate the slack for each activity. Which activities are on the critical path? Solve for "?".

Activity

Activity Time (weeks)

On Critical Path? (Answer yes or no)

Slack

(Weeks)

A

2

?

?

B

10

?

?

C

8

?

?

D

12

?

?

E

11

?

?

F

4

?

?

G

7

?

?

H

6

?

?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!