Question: A project has 75 activities but we have only a partial information as shown below: activity =F, duration =38 days,IP= not given activity =K, duration

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: activity =F, duration =38 days,IP= not given activity =K, duration =54 days,IP= not given activity =P, duration =30 days, P= not given activity =C, duration =35 days,IP= not given activity =A, duration =23 days, IP=F,K activity =L, duration =38 days, P=K,P activity =Q, duration =30 days, P=P activity =B, duration =43 days, IP=P,C If LF(A)=166,LF(L)=138,LF(Q)=189 and LF(B)=130, find the value of LS(P)