Question: A project has 75 activities but we have only a partial information as shown below: I activity =E, duration =15 days, IP= not given activity

A project has 75 activities but we have only a
A project has 75 activities but we have only a partial information as shown below: I activity =E, duration =15 days, IP= not given activity =K, duration =50 days, IP= not given activity =P, duration =34 days, IP=E activity =A, duration =44 days, IP=E activity =L, duration =60 days, IP=K,P activity =R, duration =54 days, IP=P,A activity =G, duration =71 days, IP=P,A If LF(L)=256,LF(R)=203 and LF(G)=206, then find the value of LS(E)