Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 117 0.39

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 117 0.39
B E 63 1
C D 22 0.2
D End 43 3.41
E End 33 0

What is the probability that the project will be completed within 190 days?

a.

1

b.

0

c.

0.18

d.

0.25

e.

0.82