Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 117 0.39
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 117 | 0.39 |
| B | E | 63 | 1 |
| C | D | 22 | 0.2 |
| D | End | 43 | 3.41 |
| E | End | 33 | 0 |
What is the probability that the project will be completed within 190 days?
a.
1
b.
0
c.
0.18
d.
0.25
e.
0.82