Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A 88 0.39 B E 51

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A 88 0.39 B E 51 1 C D 39 10.15 D End 14 3.46 E End 12 0 What is the probability that the project will be completed within 149 days? O a. 0 O b. 0.18 O C. 0.82 d. 1 e. 0.25