Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 45 0.26 B E

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 45 0.26 B E 17 0.25 C D 44 0.19 D End 24 0.55 E End 15 0.75 What is the probability that the project will be completed within 117 days? a. 0.25 Ob. 0.82 Oc. 0.18 Od 0 e. 1