Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 60 0.13
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 60 | 0.13 |
| B | E | 33 | 1 |
| C | D | 43 | 0.21 |
| D | End | 18 | 3.66 |
| E | End | 15 | 0 |
What is the probability that the project will be completed within 129 days?
a.
0
b.
0.18
c.
0.25
d.
1
e.
0.82
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts