Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 1109 0.12 E 38

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 1109 0.12 E 38 11 D 41 0.14 D End 41 3.74 End 22 0 What is the probability that the project will be completed within 199 days? a. 0.25 O b. 1 C. 0.18 d. 0.82 O e. 0