Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 79 0.23 B E

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 79 0.23 B E 27 0.25 C D 35 0.28 D End 40 0.49 E End 17 0.75 What is the probability that the project will be completed within 158 days? a. 0.82 b. 0.18 C. 0 d. 1 e. 0.25