Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 25 0.39 B E

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 25 0.39 B E 19 0.25 C D 44 0.21 D End 16 0.4 E End 10 0.75 What is the probability that the project will be completed within 89 days? o a. 0 b. 1 C. 0.25 d. 0.18 e. 0.82