Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 111 0.23

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 111 0.23
B E 93 1
C D 37 0.1
D End 34 3.67
E End 21 0

What is the probability that the project will be completed within 190 days?

a.

0.25

b.

0.82

c.

0.18

d.

0

e.

1