Question: Activity Description Precede Time A Requirement analysis 5 - B System design 15 A C System programing 25 B D Telecom 15 B E Hardware

Activity

Description

Precede

Time

A

Requirement analysis

5

-

B

System design

15

A

C

System programing

25

B

D

Telecom

15

B

E

Hardware installation

30

B

F

Integration

10

C,D

G

System testing

10

E,F

H

Training/support

5

G

I

Hand over and go-live

5

H

Based on the above data perform the following task

  1. Construct the network diagram
  2. Determine the number of possible phases
  3. Calculate the total expected time duration of project
  4. Determine the critical path
  5. Drive the ES,LS,EF and LF for each task using task box

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!