Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 9 D B 2 E C-D 7
| Schedule the following activities using CPM: |
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 3 | |
| B | A | 4 |
| C | A | 9 |
| D | B | 2 |
| E | C-D | 7 |
| F | D | 3 |
| G | F | 4 |
| H | E-G | 5 |
| Requirement 1: |
| What is the critical path? | |
| (Click to select) A-B-D-F-G-H A-B-D-E-H A-C-E-F-G-H A-C-E-H |
| Requirement 2: | |
| How many weeks will it take to complete the project? |
| Number of weeks |
| Requirement 3: |
| Which activities have slack? | |
| (Click to select) B-C-F-H B-D-F-G B-C-E-H B-D-F-H |