Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 9 D B 2 E C-D 7

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 9
D B 2
E C-D 7
F D 3
G F 4
H E-G 5

Requirement 1:
What is the critical path?
(Click to select) A-B-D-F-G-H A-B-D-E-H A-C-E-F-G-H A-C-E-H

Requirement 2:
How many weeks will it take to complete the project?

Number of weeks

Requirement 3:
Which activities have slack?
(Click to select) B-C-F-H B-D-F-G B-C-E-H B-D-F-H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!