Question: Activity Predecessor Time Cost Normal Crashed Normal Crashed A 15 13 20000 26000 IB 12 12 25000 25000 C B 15 13 30000 38000 D


Activity Predecessor Time Cost Normal Crashed Normal Crashed A 15 13 20000 26000 IB 12 12 25000 25000 C B 15 13 30000 38000 D 15 12 30000 36000 E D 15 12 17000 26000 IF E 15 12 23000 35000 G 16 13 50000 62000 G 16 12 40000 60000 H 16 9 45000 87000 LIVE O The normal time and the normal cost of the project. (2m) 2. The crashed time of the project (1m) 3. Fill template 1 (slopes), (4 m) The crashed cost of the project using method one, by filling template 2(7m) Activity Slope B D G H Template 2 Activity Early Start Early Late StartLate Finish TF Relax Savings Finish by 1 (Ctrl)