Given the following table:
| Activity
| Predecessor
| Time | Cost | ||
| Normal Crashed | Normal Crashed | ||||
| A | ---- | 15 | 13 | 20000 | 26000 |
| B | A | 12 | 12 | 25000 | 25000 |
| C | B | 15 | 13 | 30000 | 38000 |
| D | --- | 15 | 12 | 30000 | 36000 |
| E | D | 15 | 12 | 17000 | 26000 |
| F | E | 15 | 12 | 23000 | 35000 |
| G | --- | 16 | 13 | 50000 | 62000 |
| H | G | 16 | 12 | 40000 | 60000 |
| J | H | 16 | 9 | 45000 | 87000 |
Template 1
| Activity
| Slope
| |
| A |
|
|
| B |
|
|
| C |
|
|
| D |
|
|
| E |
|
|
| F |
|
|
| G |
|
|
| H |
|
|
| J |
|
|
Template 2
| Activity
| Early Start | Early Finish | Late Start | Late Finish | TF | Relax by | Savings |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Crashed cost