Question: Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed A 16 13 20000 26000 IB A 16 10 25000 43000 C B

Given the following table: Activity PredecessorGiven the following table: Activity PredecessorGiven the following table: Activity PredecessorGiven the following table: Activity Predecessor

Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed A 16 13 20000 26000 IB A 16 10 25000 43000 C B 15 10 30000 50000 --- 15 14 30000 31000 D 14 10 17000 25000 E 15 13 23000 29000 --- 14 13 50000 53000 IH 14 12 40000 48000 H 13 11 45000 55000 1. The normal time and the normal cost of the project. (2m) 2. The crashed time of the project (1m) 3. Fill template 1 (slopes), (3m) 4. The crashed cost of the project using method one, by filling template 2_(7m). The crashed cost of finishing the project in 41 days, by filling template 3 (7m) 5. Template 1 Activity Slope A B C D E G H Template 2 Activity Early Late TF Relax by Savings Early Late Finish Start Start Finish Template 3 Time of Critical path the project What activity to Additional cost Total cost crash, and by how much

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!