Question: Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed IA 14 10 20000 26000 18 14 25000 33000 C B 16 12

Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed IA 14 10 20000 26000 18 14 25000 33000 C B 16 12 30000 40000 D 15 12 30000 39000 E D 15 12 17000 27000 F E 15 11 23000 39000 G 13 12 50000 56000 H G 17 16 40000 45000 U H 12 12 45000 45000 LIVE 1. The normal time and the normal cost of the project. (2 m) 2. The crashed time of the project (1m) B. Fill template (slopes), (4 m) 4. The crashed cost of the project using method one by filling template 2 (Zm). Jo Type here to search Given the following table: Activity Predecessor Time Cost Normal Crashed Normal Crashed IA 14 10 20000 26000 18 14 25000 33000 C B 16 12 30000 40000 D 15 12 30000 39000 E D 15 12 17000 27000 F E 15 11 23000 39000 G 13 12 50000 56000 H G 17 16 40000 45000 U H 12 12 45000 45000 LIVE 1. The normal time and the normal cost of the project. (2 m) 2. The crashed time of the project (1m) B. Fill template (slopes), (4 m) 4. The crashed cost of the project using method one by filling template 2 (Zm). Jo Type here to search
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock