Question: ACTIVITY PREDECESSOR TIME(WEEKS) A - 14 B - 8 C - 7 D B, - 5 E C 9 F C 3 G D,E 6

ACTIVITY PREDECESSOR TIME(WEEKS)
A - 14
B - 8
C - 7
D B, - 5
E C 9
F C 3
G D,E 6
H A 4
END G, F, H

a) Draw a precedence diagram using AOA (20 points)

b) Find the critical path-based AOA. (20 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!