Question: Consider the below project information. Activity Immediate Predecessor Normal Duration (days) Normal Cost ($) Crash Duration (days) Crash Cost ($) A --- 5 100 3

Consider the below project information.

Activity

Immediate Predecessor

Normal Duration (days)

Normal Cost ($)

Crash Duration (days)

Crash Cost ($)

A

---

5

100

3

180

B

---

5

80

3

120

C

---

5

100

5

100

D

A, B

4

100

2

200

E

B

3

75

3

75

F

C

8

200

6

220

G

D, E

6

100

5

180

Q1. Reduce the project to minimum duration and calculate the final cost. (Show All Steps).

Q2. Consider the Q1. Which of the following shows the maximum number of activities we can crash to reduce the duration of the project at most 1 day? (Explain. No Explanation No Points).

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!