Question: Consider the following work breakdown structure: ActivityPrecedesDuration Estimates ( Days ) OptimisticMost LikelyPessimisticStartU,V - - - UW 3 5 5 0 6 5 VW ,

Consider the following work breakdown structure:
ActivityPrecedesDuration Estimates (Days)OptimisticMost LikelyPessimisticStartU,V---UW355065VW,X284052WZ263544XY284052YZ262938ZEnd366084
What is the probability that the critical path for this project will be completed within 200 days?
Multiple Choice
.8413
.9544
.9772
.9974
.9987