Activity Predecessor Duration (days)
A NONE 3
B NONE 3
C NONE 2
D NONE 4
E A 6
F A 5
G A 9
H C 3
I D 6
J D 5
K B 5
L B 8
M F, H, J 6
N G 4
O I, L 3
P E 6
Q N, P 2
R N, P 5
S K 7
T K 6
U M, O, Q, R, S 4