Activity Predecessor Duration (days)
A NONE 2
B A 5
C NONE 2
D C 4
E A 5
F A 5
G C 7
H C 2
I D, E 6
J B 4
K B 5
L F, G, I, K 5
M H, L 6
N H, L 3
O K 3
P K 5
Q K 5
R N, O 2