Question: PERT HOMEWORK #3 Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node,

PERT HOMEWORK #3 Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path. Activity Predecessor Duration (days) NONE A A NONE D D D B. C, E F. G H I, J G L