Question: PERT HOMEWORK #2 Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node,

PERT HOMEWORK #2 Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path. Activity Predecessor Duration (days) NONE NONE A A B B W A U D N O W N A W UN D, E D, E G. H