Question: Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the

Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path.

Activity Predecessor Duration (days)

A NONE 2

B A 3

C A 2

D C 4

E B 1

F B 2

G F 3

H D, E 3

I G 4

J H, I 5