Question: Question 1 Consider the following project schedule: ActivityImmediate PredecessorTimeESEFLSLFA - - 4 0 4 6 1 0 B - - 5 0 5 0 5
Question
Consider the following project schedule:
ActivityImmediate
PredecessorTimeESEFLSLFABCADBEBFC DGC DHE F
a Which activities are critical?
b Which activity has the most slack?